Question : A and B complete a work in 24 and 30 days, respectively, working 10 hours per day. The work is to be done in two shifts. The morning shift is for 6 hours and the evening shift is for 4 hours. On the first day, A works in the morning and B works in the evening, and they interchange their shifts every day. On which day did the work get completed?
Option 1: 21st day
Option 2: 24th day
Option 3: 30th day
Option 4: 27th day
Correct Answer: 27th day
Solution :
Given:
A can complete the whole work in 24 days.
B can complete the whole work in 30 days.
Now,
Total work = LCM of 24 and 30 = 120
Efficiency of A = $\frac{120}{24}$ = 5
Efficiency of B = $\frac{120}{30}$ = 4
Since Work done by A and B in 10 hours of one day is 5 and 4 respectively.
Work done by A and B in two days = 5 + 4 = 9 days
A and B repeat the same process on all 26 days
Work completed by A and B in 26 days = 9 × 13 =117
Remaining work = 120 – 117 = 3
Efficiency of A and B in 2 days = 5 + 4 = 9
so,
3 part work will be completed in = $\frac{2}{3}$ days
The total time taken to complete the work = $26\tfrac{2}{3}$ days
So, the total work is completed on the 27th day.
Hence, the correct answer is the 27th day.
Related Questions
Know More about
Staff Selection Commission Sub Inspector ...
Application | Eligibility | Selection Process | Result | Cutoff | Admit Card | Preparation Tips
Get Updates BrochureYour Staff Selection Commission Sub Inspector Exam brochure has been successfully mailed to your registered email id “”.