Question : A alone can do a piece of work in 10 days. B alone can do the same work in 12 days. They work on alternate days starting with A. In how many days will they complete $\frac{3}{4}$th of the total work?
Option 1: $\frac{47}{3}$ days
Option 2: $\frac{50}{3}$ days
Option 3: $\frac{53}{6}$ days
Option 4: $\frac{49}{6}$ days
New: SSC MTS Tier 1 Answer key 2024 out
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $\frac{49}{6}$ days
Solution : Given: A alone can do a piece of work in 10 days. B alone can do the same work in 12 days. They work on alternate days starting with A. Total work = Time × Efficiency The total work done overall = LCM(10, 12) = 60 A's efficiency $=\frac{60}{10}=6$ B's efficiency $=\frac{60}{12}=5$ Total work of two days = 5 + 6 = 11 The $\frac{3}{4}$ of the total work = $60\times \frac{3}{4}$ = 45 The time taken to complete 44 work = $\frac{44}{11}$ = 4 pair = 4 × 2 = 8 days And A will work once more the following day to finish the remaining unit work = $\frac{1}{6}$ The number of days will they complete $\frac{3}{4}$ of the total work $=8+\frac{1}{6}= \frac{48+1}{6}=\frac{49}{6}$ days Hence, the correct answer is $\frac{49}{6}$ days.
Application | Cutoff | Selection Process | Preparation Tips | Eligibility | Exam Pattern | Admit Card
Question : X alone can complete a piece of work in 16 days, while Y alone can complete the same work in 24 days. They work on alternate days starting with Y. In how many days will 50% of the total work be completed?
Option 1: $\frac{24}{3}$ days
Option 2: $\frac{29}{3}$ days
Option 3: $\frac{32}{3}$ days
Option 4: 9 days
Question : Akbar can complete a piece of work alone in 12 days, while Anthony can complete the same work alone in 20 days. If they work on alternate days with Anthony starting the work, then in how many days can they complete the whole work?
Option 1: $15$ days
Option 2: $16$ days
Option 3: $14 \frac{4}{5}$ days
Option 4: $15 \frac{1}{5}$ days
Question : $\mathrm{N}_1$ alone can do 20% of a piece of work in 6 days, $\mathrm{N}_2$ alone can do 20% of the same work in 4 days, and $\mathrm{N}_3$ alone can do 50% of the same work in 12 days. In how many days can they complete the work, if all of them work together?
Option 1: 10 days
Option 2: $\frac{120}{13}$ days
Option 3: 8 days
Option 4: $\frac{120}{17}$ days
Question : Avi alone can do a piece of work in 60 days while Prakash alone can do it in 80 days. In how many days will they finish it together?
Option 1: $\frac{250}{6}$ days
Option 2: $\frac{270}{6}$ days
Option 3: $\frac{240}{7}$ days
Option 4: $\frac{140}{6}$ days
Question : S alone can do a piece of work in 14 days. T alone can do the same work in 21 days. U alone can do the same work in 28 days. Working together, in how many days will they complete the work?
Option 1: $\frac{84}{13}$ days
Option 2: $\frac{77}{13}$ days
Option 3: $\frac{71}{13}$ days
Option 4: $\frac{87}{13}$ days
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile