A and B together do a work in 6 days.A alone do it in 9 days?How many days taken by B to conplete the same work alone?


sagar singh 29th Apr, 2019
Answer (1)
Tamajit Biswas Student Expert 20th Jul, 2019

Hi Sagar,

Please use this platform to ask questions related to information about various entrance examinations, colleges or universities, etc in the future. 

Now to answer your question,

In 6 days, A and B both complete a work.

In 1 day, they both do 1/6 work.

In 9 days A does a work.

In 1 day, A does 1/9  work.

Therefore, in one day B does (1/6-1/9) work, i.e. 1/18 work.

Thus, B will take 36 days to complete the same work.

BEST WISHES!

Related Questions

UPES B.Tech Admissions 2026
Apply
Ranked #43 among Engineering colleges in India by NIRF | Highest Package 1.3 CR , 100% Placements
UPES Integrated LLB Admission...
Apply
Ranked #18 amongst Institutions in India by NIRF | Ranked #1 in India for Academic Reputation by QS Rankings | 16 LPA Highest CTC
Presidency University MBA Adm...
Apply
NAAC A+ Accredited | Highest CTC 10 LPA | Top Recruiters : Amazon, Accenture, KPMG, EY, Capgemini & many more
Nirma University Law Admissio...
Apply
Grade 'A+' accredited by NAAC | Ranked 33rd by NIRF 2025
UPES M.Tech Admissions 2026
Apply
Ranked #45 Among Universities in India by NIRF | 1950+ Students Placed 91% Placement, 800+ Recruiters
UPES | BBA Admissions 2026
Apply
#36 in NIRF, NAAC ‘A’ Grade | 100% Placement, up to 30% meritorious scholarships
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books