Question : A, B, and C can finish a work in 15 days working alternately in the same order. The efficiency of A is the same as that of B and the efficiency of C is equal to that of A. In how many days will the work be finished if they work alternately in the order C, A, and B?

Option 1: 12

Option 2: 14

Option 3: 15

Option 4: 16


Team Careers360 14th Jan, 2024
Answer (1)
Team Careers360 18th Jan, 2024

Correct Answer: 15


Solution : The efficiency of A is the same as that of B and the efficiency of C is equal to that of A.
Let the efficiency of B is $x$.
Then the efficiency of A is $x$.
Also, the efficiency of C would be $x$.
Since the efficiency is the same, A, B, and C working in any order would take 15 days to complete the work.
Hence, the correct answer is 15.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

Amity Online MBA
Apply
Apply for an Online MBA from Amity Online.
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books