Question : Aadish can complete a work in 14 days. If he worked for 8 days, then what fraction of the work would be left?

Option 1: $\frac{2}{7}$

Option 2: $\frac{3}{7}$

Option 3: $\frac{4}{7}$

Option 4: $\frac{1}{7}$


Team Careers360 18th Jan, 2024
Answer (1)
Team Careers360 21st Jan, 2024

Correct Answer: $\frac{3}{7}$


Solution : If Aadish can complete the work in 14 days, then in 1 day he completes $\frac{1}{14}$ of the work. 
So, in 8 days, he completes $=8 \times \frac{1}{14}= \frac{8}{14} = \frac{4}{7}$ of the work.
Therefore, the fraction of the work that is left $=1 - \frac{4}{7} = \frac{3}{7}$
Hence, the correct answer is $\frac{3}{7}$.

Know More About

Related Questions

Amity Online MBA
Apply
Apply for an Online MBA from Amity Online.
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books