Question : P can do $ \frac{1}{4} $th of work in 10 days, Q can do 40% of work in 40 days and R can do $\frac{1}{3} $rd of work in 13 days. Who will complete the work first?
Option 1: P
Option 2: Q
Option 3: R
Option 4: both P and R
New: SSC CGL 2025 Tier-1 Result
Latest: SSC CGL complete guide
Suggested: Month-wise Current Affairs | Upcoming Government Exams
Correct Answer: R
Solution : P can do $\frac{1}{4}$th of work in 10 days. ⇒ To complete the work, P will take 10 × 4 = 40 days Q can do $\frac{2}{5}$th of work in 40 days. ⇒ To complete the work, Q will take 40 × $\frac{5}{2}$ = 100 days R can do $\frac{1}{3}$rd of work in 13 days. ⇒ To complete the work, R will take 13 × 3 = 39 days So, R will complete the work first. Hence, the correct answer is R.
Candidates can download this ebook to know all about SSC CGL.
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile