Question : The technique of work measurement aims to:

 

Option 1: Assess employee job satisfaction

Option 2: Evaluate employee performance

Option 3: Determine the time required to complete a task

Option 4: Calculate employee wages and salaries


Team Careers360 6th Jan, 2024
Answer (1)
Team Careers360 10th Jan, 2024

Correct Answer: Determine the time required to complete a task


Solution : The correct answer is (c) Determine the time required to complete a task.

Work measurement is a technique used to determine the time required to complete a specific task or activity. It involves analyzing and measuring the elements and steps involved in a task, such as the time taken to perform each step, the required resources, and the level of effort. Work measurement techniques, such as time studies and predetermined motion time systems, help in establishing standard times for tasks, estimating workloads, setting productivity targets, and optimizing resource allocation.

Related Questions

Amity University | M.Tech Adm...
Apply
Ranked amongst top 3% universities globally (QS Rankings).
Shoolini University Admission...
Apply
NAAC A+ Grade | Ranked No.1 Private University in India (QS World University Rankings 2025)
Amity University Noida B.Tech...
Apply
Among Top 30 National Universities for Engineering (NIRF 2024) | 30+ Specializations | AI Powered Learning & State-of-the-Art Facilities
Amity University Noida MBA Ad...
Apply
Amongst top 3% universities globally (QS Rankings)
Amity University, Noida BBA A...
Apply
Ranked amongst top 3% universities globally (QS Rankings)
Graphic Era (Deemed to be Uni...
Apply
NAAC A+ Grade | Among top 100 universities of India (NIRF 2024) | 40 crore+ scholarships distributed
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books