worker a completes a task in 8 days and worker b completes the same task in 10 days. if both a and b work together, in how many days they will complete the task?


Bunny 20th Oct, 2020
Answer (1)
NAVYA BOINPALLY Student Expert 20th Oct, 2020

Hi,

Worker A completes the task in 8 days. So in one day he will complete 1/8 part of the task.

So, A's one day work = 1/8

similarly, B's one day work = 1/10

(A+B)'s one day work = 1/8+ 1/10 = 9/40

9/40 of the task is completed in one day so both will complete the whole task in 40/9 days

Hopefully this is helpful,

Thankyou.

1 Comment
Comments (1)
10th Mar, 2022
Hello, how and why did the answer came out as 40/9 ?
Please make me understand 🙏🏻
Reply

Related Questions

MAHE Manipal M.Tech 2025
Apply
NAAC A++ Accredited | Accorded institution of Eminence by Govt. of India | NIRF Rank #4
Graphic Era (Deemed to be Uni...
Apply
NAAC A+ Grade | Among top 100 universities of India (NIRF 2024) | 40 crore+ scholarships distributed
Amity University Noida B.Tech...
Apply
Among Top 30 National Universities for Engineering (NIRF 2024) | 30+ Specializations | AI Powered Learning & State-of-the-Art Facilities
JSS University Mysore BBA Adm...
Apply
NAAC A++ Accredited| Ranked #24 in University Category by NIRF
JSS University Noida MBA 2025
Apply
170+ Recruiters Including Samsung, Zomato, LG, Adobe and many more | Highest CTC 47 LPA
UPES B.Tech Admissions 2025
Apply
Ranked #42 among Engineering colleges in India by NIRF | Highest Package 1.3 CR , 100% Placements | Last Date to Apply: 29th May
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books