Worker A completes the task in 8 days. So in one day he will complete 1/8 part of the task.
So, A's one day work = 1/8
similarly, B's one day work = 1/10
(A+B)'s one day work = 1/8+ 1/10 = 9/40
9/40 of the task is completed in one day so both will complete the whole task in 40/9 days
Hopefully this is helpful,
Thankyou.
Question : A and B together can complete a work in 20 days. B and C together can complete the same work in 15 days. If A, B, and C all work together, then the same work gets completed in 10 days. How many days will A and C together take to complete the same work?
Question : A and B together can complete a given work in 10 days. C can complete the same work alone in 15 days. In how many days can they complete the work, if all three work together?
Question : A and B together complete a work in 20 days, B and C together complete the same work in 30 days, and C and A together complete the same work in 24 days. In how many days A, B, and C together can complete the same work?
Question : A can complete a piece of work in 9 days. B and C can complete the same work in 12 days and 18 days respectively. If A, B, and C work together, then in how many days will they complete the work?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile