Question : X, Y, and Z can complete a piece of work in 20, 12, and 28 days respectively. If all work together, the approximate number of days to complete the work will be:
Option 1: 6
Option 2: 7
Option 3: 4
Option 4: 5
Recommended: How to crack SSC CHSL | SSC CHSL exam guide
Don't Miss: Month-wise Current Affairs | Upcoming government exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 6
Solution : The time taken by X, Y, and Z to complete the work is 20, 12, and 28 days respectively. Work done by X, Y, and Z in a day is $\frac{1}{20}$, $\frac{1}{12}$, and $\frac{1}{28}$ respectively. Work done by X, Y, and Z together in a day = $\frac{1}{20}+\frac{1}{12}+\frac{1}{28}$ = $\frac{71}{420}$ So, time is taken by X, Y, and Z to complete the work together = $ \frac{420}{71}\approx$ 6 days Hence, the correct answer is 6.
Candidates can download this e-book to give a boost to thier preparation.
Application | Eligibility | Admit Card | Answer Key | Preparation Tips | Result | Cutoff
Question : X can do a piece of work in 14 days, Y can do the same work in 28 days and Z can do it in 42 days. In how many days can X, Y, and Z together complete the work?
Option 1: $7 \frac{9}{11}$
Option 2: $7 \frac{7}{11}$
Option 3: $7 \frac{5}{11}$
Option 4: $7 \frac{3}{11}$
Question : x, y, and z are 3 values, such that x + y = 12, y + z = 17 and z + x = 19. What is the average of x, y, and z?
Option 1: 10
Option 2: 8
Option 3: 6
Option 4: 4
Question : If $x(x+y+z)=20$, $y(x+y+z)=30$, and $z(x+y+z)=50$, then the value of $2(x+y+z)$ is:
Option 1: 20
Option 2: –10
Option 3: 15
Option 4: 18
Question : A can complete a piece of work in 9 days. B and C can complete the same work in 12 days and 18 days respectively. If A, B, and C work together, then in how many days will they complete the work?
Option 1: 10 days
Option 2: 8 days
Option 3: 4 days
Option 4: 15 days
Question : If 4 men or 6 women can do a piece of work in 12 days, working 7 hours a day. How many days will it take to complete a work twice as large, with 10 men and 3 women working together 8 hours a day?
Option 1: 6 days
Option 2: 7 days
Option 3: 8 days
Option 4: 10 days
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile