Solution : Given: 60 men can complete a work in 40 days.
Total work = 60 × 40 = 2400 units
60 men worked in 10 days = 600 units
55 men worked in 10 days = 550 units
50 men worked in 10 days = 500 units
45 men worked in 10 days = 450 units
Total work left = 2400 – (600 + 550 + 500 + 450)
= 2400– 2100
= 300 units
Now, 40 men will do 300 units in = $\frac{300}{40}$
= 7.5
Total number of days to finish the work = 40 + 7.5 = 47.5 days
Hence, the correct answer is 47.5.

Know More About

Related Questions

TOEFL ® Registrations 2025
Apply
Accepted by 13,000 universities worldwide | Offered in 200+ countries | 40 million people have taken TOEFL Test
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books