Question : A can do a piece of work in 48 days. If B is 50% more efficient than A, then in how many days can B do the same work?

Option 1: 24

Option 2: 32

Option 3: 18

Option 4: 15


Team Careers360 13th Jan, 2024
Answer (1)
Team Careers360 21st Jan, 2024

Correct Answer: 32


Solution : Let the total work to be done = 1
Then, A's one day work= $\frac{\text{(total work)}}{ \text{(total days taken by A)}} =\frac{1}{48}$
B's one-day work = 150% of A's one-day work (because B is 50% more efficient)
$=\frac{1}{48}\times\frac{150}{100}=\frac{1}{32}$
Total time taken by B to do total work= $\frac{1}{\frac{1}{32}}=32$ days
Hence, the correct answer is 32.

Know More About

Related Questions

Amity Online MBA
Apply
Apply for an Online MBA from Amity Online.
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books