12 Views

Question : A can do a work in 48 days. What part of the total work can be done by A in 18 days?

Option 1: $\frac{5}{6}$

Option 2: $\frac{3}{5}$

Option 3: $\frac{3}{8}$

Option 4: $\frac{4}{9}$


Team Careers360 18th Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: $\frac{3}{8}$


Solution : A can complete the work in 48 days.
⇒ 1 day work of A = $\frac{1}{48}$
Work done by A in 18 days = $\frac{1}{48}×18$ = $\frac{18}{48} = \frac{3}{8}$
Hence, the correct answer is $\frac{3}{8}$.

Know More About

Related Questions

Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books