Question : A can do a work in 48 days. What part of the total work can be done by A in 18 days?
Option 1: $\frac{5}{6}$
Option 2: $\frac{3}{5}$
Option 3: $\frac{3}{8}$
Option 4: $\frac{4}{9}$
New: SSC MTS Tier 1 Answer key 2024 out
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $\frac{3}{8}$
Solution : A can complete the work in 48 days. ⇒ 1 day work of A = $\frac{1}{48}$ Work done by A in 18 days = $\frac{1}{48}×18$ = $\frac{18}{48} = \frac{3}{8}$ Hence, the correct answer is $\frac{3}{8}$.
Application | Cutoff | Selection Process | Preparation Tips | Eligibility | Exam Pattern | Admit Card
Question : A can do a piece of work in 5 days and B in 4 days. How long will they take to do the same work when working together?
Option 1: $9$ days
Option 2: $2\frac{2}{9}$ days
Option 3: $4\frac{1}{3}$ days
Option 4: $3\frac{2}{9}$ days
Question : A, B, and C can do a piece of work in 10, 20, and 30 days, respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Option 1: 9 days
Option 2: $8 \frac{5}{11}$ days
Option 3: $8 \frac{2}{11}$ days
Option 4: $6 \frac{5}{11}$ days
Question : A can do one and a half as much work as B can do in one day. B alone can do a piece of work in 18 days. They together can finish that work in:
Option 1: $10\frac{1}{5}$ days
Option 2: $11\frac{1}{5}$ days
Option 3: $5\frac{1}{5}$ days
Option 4: $7\frac{1}{5}$ days
Question : A alone can do $\frac{1}{4}$th part of the work in 12 days. B alone can do $\frac{1}{5}$th part of the work in 4 days. In how many days can A and B together can do the same work?
Option 1: $\frac{330}{13}$ days
Option 2: $\frac{240}{17}$ days
Option 3: $\frac{210}{4}$ days
Option 4: $\frac{255}{7}$ days
Question : A alone can do a piece of work in 10 days. B alone can do the same work in 12 days. They work on alternate days starting with A. In how many days will they complete $\frac{3}{4}$th of the total work?
Option 1: $\frac{47}{3}$ days
Option 2: $\frac{50}{3}$ days
Option 3: $\frac{53}{6}$ days
Option 4: $\frac{49}{6}$ days
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile