Question : A can do the same work in 8 days, B can do the same work in 10 days, and C can do the same work in 12 days. If all three of them do the same work together and they are paid Rs. 7400, what is the share (in Rs.) of B?
Option 1: 2600
Option 2: 3000
Option 3: 2400
Option 4: 2000
Latest: SSC CGL 2024 final Result Out | SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL Tier 1 Scorecard 2024 Released | SSC CGL complete guide
Suggested: Month-wise Current Affairs | Upcoming Government Exams
Correct Answer: 2400
Solution : Let total work to be done = LCM (8, 10, 12) = 120 units A can do the work in 8 days. ⇒ A's efficiency = $\frac{120}{8} = 15$ units/day Similarly, B's efficiency = $\frac{120}{10} = 12$ units/day and C's efficiency = $\frac{120}{12} = 10$ units/day Total amount to be paid = Rs. 7400 $\therefore$ B's share $=\frac{12}{15+12+10}×7400=2400$ Hence, the correct answer is 2400.
Candidates can download this ebook to know all about SSC CGL.
Admit Card | Eligibility | Application | Selection Process | Preparation Tips | Result | Answer Key
Question : A and B together can do a piece of work in 36 days and B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in:
Option 1: 8 days
Option 2: 16 days
Option 3: 30 days
Option 4: 32 days
Question : A and B can do a work in 8 days and B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in:
Option 1: 4 days
Option 2: 6 days
Option 3: 8 days
Option 4: 12 days
Question : A can do $\frac{1}{3}$ of a work in 30 days. B can do $\frac{2}{5}$ of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:
Option 1: 15 days
Option 2: 10 days
Option 3: 18 days
Question : A and B do $\frac{3}{5}$th part of a work and the rest of the work is completed by C. If A, B, and C take the same work for Rs. 5000, then what is the share of C (in Rs.)?
Option 1: 3000
Option 2: 2500
Option 3: 2000
Option 4: 1500
Question : A, B, and C can work together for Rs. 550. A and B together are to do $\frac{7}{11}$ of the work. The share of C should be:
Option 1: Rs. 200
Option 2: Rs. 300
Option 3: Rs. 400
Option 4: Rs. 450