7 days in seconds are 604,800 and 3 days in seconds are 259200.
Question : A can do a piece of work in 9 days, while B can do it in 12 days. A and B together can do the work in:
Option 1: $5\frac{1}{7}$ days
Option 2: $5\frac{2}{7}$ days
Option 3: $6\frac{1}{7}$ days
Option 4: $6\frac{2}{7}$ days