Question :

 Identify the correct sequence of the Controlling process :

(A) Analysing deviations

(B) Measurement of actual performance

(C) Setting up standards

(D) Comparison of actual performance with standards

 

Choose the correct answer from the options below:

 

Option 1: (A), (B), (C), (D)

Option 2:  (A), (C), (B), (D)

Option 3:  (B), (A), (D), (C)

Option 4: (C), (B), (D),(A)


Team Careers360 1st Jan, 2024
Answer (1)
Team Careers360 22nd Jan, 2024

Correct Answer: (C), (B), (D),(A)


Solution : Following is the correct sequence of the controlling process: Setting up standards, Measurement of actual performance, Comparison of actual performance with standards, and Analysing deviations. Hence, (C), (B), (D), (A) are correct answers.

Related Questions

MAHE Manipal M.Tech 2025
Apply
NAAC A++ Accredited | Accorded institution of Eminence by Govt. of India | NIRF Rank #4
Graphic Era (Deemed to be Uni...
Apply
NAAC A+ Grade | Among top 100 universities of India (NIRF 2024) | 40 crore+ scholarships distributed
Indrashil University | B.Tech...
Apply
Apply for B.Tech | AICTE Aproved | UGC Recognized | International Collaborations for Global Edge | 100% Placement Assistance
Manav Rachna-MBA Admissions 2025
Apply
41000+ Alumni network | Students from over 20 countries
Manav Rachna-B.Tech Admission...
Apply
NAAC A++ Grade | NBA Accredited B.Tech programs | 41000+ Alumni network | Students from over 20 countries
JSS University Noida MBA 2025
Apply
170+ Recruiters Including Samsung, Zomato, LG, Adobe and many more | Highest CTC 47 LPA
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books