Question :

 Identify the correct sequence of the Controlling process :

(A) Analysing deviations

(B) Measurement of actual performance

(C) Setting up standards

(D) Comparison of actual performance with standards

 

Choose the correct answer from the options below:

 

Option 1: (A), (B), (C), (D)

Option 2:  (A), (C), (B), (D)

Option 3:  (B), (A), (D), (C)

Option 4: (C), (B), (D),(A)


Team Careers360 1st Jan, 2024
Answer (1)
Team Careers360 22nd Jan, 2024

Correct Answer: (C), (B), (D),(A)


Solution : Following is the correct sequence of the controlling process: Setting up standards, Measurement of actual performance, Comparison of actual performance with standards, and Analysing deviations. Hence, (C), (B), (D), (A) are correct answers.

Related Questions

Amity University, Noida Law A...
Apply
700+ Campus placements at top national and global law firms, corporates and judiciaries
Amity University, Noida BBA A...
Apply
Ranked amongst top 3% universities globally (QS Rankings)
VIT Bhopal University | M.Tec...
Apply
M.Tech admissions open @ VIT Bhopal University | Highest CTC 52 LPA | Apply now
Amity University | M.Tech Adm...
Apply
Ranked amongst top 3% universities globally (QS Rankings).
Graphic Era (Deemed to be Uni...
Apply
NAAC A+ Grade | Among top 100 universities of India (NIRF 2024) | 40 crore+ scholarships distributed
Amity University Noida B.Tech...
Apply
Among Top 30 National Universities for Engineering (NIRF 2024) | 30+ Specializations | AI Powered Learning & State-of-the-Art Facilities
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books