Question : Rohan alone can do a work in 10 days and Mohan alone can do the same work in 15 days. In how many days will they together complete the same work?
Option 1: 6 days
Option 2: 5 days
Option 3: 4 days
Option 4: 7 days
New: SSC MTS Tier 1 Answer key 2024 out
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 6 days
Solution : Time taken by Rohan to do the work = 10 days Part of work done by Rohan in a day = $\frac{1}{10}$ Time taken by Mohan to do the work = 15 days Part of work done by Rohan in a day = $\frac{1}{15}$ Part of the work done by Rohan and Mohan in a day = $\frac{1}{10}$ + $\frac{1}{15}$ = $\frac{3+2}{30}$ = $\frac{1}{6}$ Time taken by Rohan and Mohan to do the work = 6 days Hence, the correct answer is 6 days.