A and B working together can complete a job in 30 days.The ratio of their efficiencies is 3:2 .In how many days can the faster person complete the job


Simran 9th Jan, 2020
Answer (1)
KUNAL LANJEWAR 14th Jan, 2020

Hello,

The efficiencies of work done by A and B are in the ratio 3 : 2

So, the work done by A in x days will be 5x / 3

and the work done by B in x days will be 5x / 2

Given that A and B together complete the work in 30 days.

The efficiency of A to that of B is in the ratio 3:2, that means A is the fastest person.

So, as concluded above, A can complete the work in 5x / 3 days

For 30 days, x = 30

So, A can complete the work in 5 x 30 / 3 days

So, A can complete the work in 50 days.

So, In 50 days, the faster person can complete the job.

Best Wishes.

Amity University Noida B.Tech...
Apply
Among Top 30 National Universities for Engineering (NIRF 2024) | 30+ Specializations | AI Powered Learning & State-of-the-Art Facilities
Amrita University B.Tech 2026
Apply
Recognized as Institute of Eminence by Govt. of India | NAAC ‘A++’ Grade | Upto 75% Scholarships
UPES Integrated LLB Admission...
Apply
Ranked #18 amongst Institutions in India by NIRF | Ranked #1 in India for Academic Reputation by QS Rankings | 16 LPA Highest CTC
Great Lakes Institute of Mana...
Apply
Admissions Open | Globally Recognized by AACSB (US) & AMBA (UK) | 17.8 LPA Avg. CTC for PGPM 2025
Jain University, Bangalore - ...
Apply
NAAC A++ Approved | Curriculum Aligned with BCI & UGC
Amity University, Mumbai Law ...
Apply
Ranked as India’s #1 Not for profit pvt. University by India Today
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books