Question : 14 people can do work in 28 days. In how many days, can 8 people complete double the work?
Option 1: 55 days
Option 2: 98 days
Option 3: 80 days
Option 4: 32 days
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
Correct Answer: 98 days
Solution :
Let the total work = 14 × 28 = 392 units
Time taken by 8 people to do the double work
= $\frac{2×392}{8}$
= 2 × 49
= 98 days
Hence, the correct answer is 98 days.