A AND B CAN TOGETHER FINSIH A WORK IN 30 DAYS.THEY WORKED TOGETHER FOR 20 DAYS AND THEN B LEFT. AND A FINISHED THE REMAINING WORK IN 20 DAYS SO, A CAN FINSIH WORK WHOLE WORK IN
Answer (1)
A and B can finish a task in 30 days.
So in 20 days A and B finish 20/30 th part of the task.
Hence remaining task is 1/3.
A finishes remaining work in 20 days
Hence A needs 20 days for doing 1/3 task
Hence A would need 20*3 =60 days to complete the whole task which was done by A and B together in 30 days.
So in 20 days A and B finish 20/30 th part of the task.
Hence remaining task is 1/3.
A finishes remaining work in 20 days
Hence A needs 20 days for doing 1/3 task
Hence A would need 20*3 =60 days to complete the whole task which was done by A and B together in 30 days.