Question : A, B, and C can separately do work in 6, 10, and 15 days respectively. They started to work together but C left after 2 days. In how many days will the remaining work be finished?
Option 1:
Option 2:
Option 3:
Option 4:
Correct Answer:
Solution :
Given, A, B, and C can separately do a work in 6, 10, and 15 days, respectively.
Work done by A in a day=
Work done by B in a day =
Work done by C in a day =
Work done by A, B, and C together in a day =
Work done by A, B, and C together in 2 days =
Work left for A and B to do =
Work done by A and B together in 1 day =
Hence, the correct answer is
SSC CGL Complete Guide
Candidates can download this ebook to know all about SSC CGL.