Question : A can do a piece of work in 6 days, working 8 hours a day, while B can do the same work in 4 days, working 10 hours a day. If the work has to be completed in 5 days, how many hours do they need to work together in a day?
Option 1:
Option 2:
Option 3:
Option 4:
Correct Answer:
Solution :
Part of the work A completes in an hour in a single day
Part of the work B completes in an hour in a single day
Let the number of hours needed to work together in a day be
According to the question,
⇒
⇒
Hence, the correct answer is