Question : A can finish a work in 20 days and B can complete the same work in 15 days. B worked for 9 days and left the job. In how many days can A alone finish the remaining work?
Option 1: 10 days
Option 2: 8 days
Option 3: 9 days
Option 4: 7 days
Correct Answer: 8 days
Solution :
Work done by A in 1 day
Work done by B in 1 day
So, work done by A in 9 days
So, Remaining work = (
Hence, the correct answer is 8 days.