Question : Anil is 12.5% more efficient than Sachin. If Sachin alone can finish a work in 10 days, then in how many days will Anil alone finish the same work?
Option 1:
Option 2:
Option 3:
Option 4:
Correct Answer:
Solution :
Time taken by Sachin to do the work = 10 days
Efficiency of Sachin =
Efficiency of Anil =
=
=
=
Time taken by Anil to do the work =
Hence, the correct answer is