Question : If 450 men can finish the construction of an apartment in 20 days, then how many men are needed to complete the same work in 30 days?
Option 1: 150
Option 2: 300
Option 3: 400
Option 4: 250
New: SSC CGL 2025 Tier-1 Result
Latest: SSC CGL complete guide
Suggested: Month-wise Current Affairs | Upcoming Government Exams
Correct Answer: 300
Solution :
We know, $M_1D_1= M_2D_2,$
Where, $M_1$ and $M_2$ are men and $D1$ and $D_2$ are days.
450 men can finish the construction of an apartment in 20 days.
Here, $M_1=450, D_1=20,$ and $D_2=30$
So, $450×20=M_2×30$
$\therefore M_2=300$
Hence, the correct answer is 300.