Question : Planning is first and foremost an activity to achieve desired results. In the context of planning. Which of the following is not correct?
Option 1: Planning is one time process
Option 2: Planning focuses on achieving objective
Option 3: Planning affect profitability
Option 4: Planning is futuristic
Correct Answer: Planning is one time process
Solution :
Planning is a never-ending or continuous process because, after making plans, one must also keep up with changes in the changing environment and choose the best way.
Hence, option 1 is the correct answer.