Question : A alone can finish a work in 15 days. A works only for the first two days and the last two days. The rest work is done by B and the work is completed in 20 days. In how many days A and B together can finish the work?
Option 1:
Option 2:
Option 3:
Option 4:
Correct Answer:
Solution :
Time taken by A alone to do the work = 15
Work done by A alone in a day =
Work done by A in the first and last two days =
Work done by B in 16 days = 1 –
Work done by B alone in a day =
Work done by A and B together in a day
=
=
=
Hence, the correct answer is
SSC CGL Complete Guide
Candidates can download this ebook to know all about SSC CGL.