Question : A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days will A, B, and C finish it, working all together?
Option 1:
Option 2:
Option 3:
Option 4:
Correct Answer:
Solution :
Given:
A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days.
A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days.
So, A in 1 day can do
B in 1 day can do
and C in 1 day can do
Now A, B, and C together in 1 day can do (
= (
Therefore, they together will finish the work in (1 ÷
Hence, the correct answer is